Enbridge Expander
Expander Addition at Everett M&R Station 00027
Enbridge sought expertise to design a low-velocity bypass (Expander) at the inlet of Station 00027 located in Everett, MA, to capture any liquids from the pipeline before it passed through the facility’s metering and regulation equipment causing potential damage.
ODIN designed a low velocity 30” Expander for their 16” station inlet feed. The larger diameter of the expander causes a reduction in gas velocity, allowing entrained liquids to drop out of the flow and collect at the bottom of the expander. The design also included inlet, outlet, and bypass valves.
A bridle/sump assembly was also installed, as liquids fill the sump, which is equipped with level switches an alarm signal is provided to Enbridge’s RTU alerting gas control of the liquids present. A second alarm also notifies them of a “high level” condition. The expander also includes vents and a drain for blow-down and liquid removal. The expander and associated equipment were supported by pile foundations designed by ODIN.
This project is commissioned and functions as desired.
Back to Project PortfolioMarkets and Services Provided
Natural Gas
Metering and Regulation
Design
ODIN is a Proud Member of These Industry Organizations
Contact Us
Main Office
2 Highwood Dr.
Suite 204
Tewksbury, MA 01876
New Jersey Office
28 Valley Rd.
Montclair, NJ 07042
PA Office
100 Front St.
Suite 900
West Conshohocken, PA 19428
AICPA–SOC 2 Type 2 Compliant
Tier 3 assessment for PSE&G
Silver Award, Enbridge